New MRL Complete Building Strip Out

New MRL Complete Building Strip Out

 

Works Completed

  • Entire strip out of the building with 17,700m2 of floor plate – 7 floors
  • Furniture, flushed plasterboard and glazed partitions, ceilings, floor finishes, amenities & kitchens
  • Class 1 Demolitions Removal of entire 12th floor. removal of roof sheeting, insulation, purlins.
  • Removed external tiles and screed on 12th floor using 5t excavator, lifted to the 12th floor by crane.
  • Removed brickwork from 7 floors of amenities, using alimac
  • Oxy cut steel roof frame and dismantled using spider crane.
  • Use of 1000t crane to remove dismantled roof structure to ground floor for removal from site.
  • Floor grinding of 17,700m2 to remove carpet adhesive

Waste Management

Waste separated at site level for safe and efficient safe removal

  • Recycled Waste included, Furniture, general waste, timber, glass, steel, aluminum, copper and rubble
  • Non Recycled materials – general waste